Pat Munro Surfacing working the nightshift
Posted on
Pat Munro Surfacing recently worked through the night successfully resurfacing the level crossing on the main Inverness to Aberdeen rail line at Insch. It’s the second level crossing the team have completed recently with the first being at Nigg.
Work involved the surface being planed to a 100mm depth, then binder and HRA reinstated to let the liners get the road markings down and all in a 10 hour possession of the crossing!